Reference
YEAR |
CUSTOMER |
SITE |
WORKS |
2005 |
EMS
|
Off-shore Ravenna
|
Connection "Ravennamare - Angela ptf.". Repair by our “Emergency Team” service of a 10 kV extruded submarine cable with supply of no. 2 PCS repair joints, execution and laying; insertion 10 kV spare cable from EMS stock.
|
2006 |
ENEL Distribuzione S.p.A. |
Sardinia |
Connection "Stintino - Asinara" - Repair by our “Emergency Team” service of a 30 kV submarine EPR insulated cable with execution of no. 2 PCS special submarine joints
|
2007 |
Dynamic Industries (USA) |
Banzala Lago (Angola) |
Repair of submarine composite cable connection between Banzala A - C platforms with supply and installation of no. 2 universal submarine joints, relocation of cable for jointing operations, laying of the spare cable and repaired connection testing. |
2007 |
ENEL Distribuzione S.p.A. |
Elba Island - Tuscany |
Connection "Elba - Pianosa" - Repair by our “Emergency Team” service of a 30 kV submarine EPR insulated cable with execution of no. 1 PCS special submarine joint, supply and installation of iron cast shell protection and stabilisation system.
|
2009 |
ARAMCO |
Safaniyah Field |
Repair of the 5 kV composite submarine XLPE insulated cable connecting MRJN 121/126 platforms with execution of no. 2 PCS special submarine joints and insertion of a spare cable coming from Aramco stocks. |